Tampa International Airport (TIA) is nearly finished with the first phase of its roughly $2.3 billion expansion. The first phase has included the construction of one of the largest car rental facilities in the country (2.6 million square feet), and a 1.4 mile people mover track, plus renovations to each of the four existing airsides and a major remodel of the main terminal.

The expansion will make travel easier for the over 18 million passengers that pass through Tampa International Airport every year. The project is also positions TIA — currently the nation’s 29th largest — for future growth. Future phases call for a 17 acre development that will include an office building, gas station, hotel and a brand new airside with 16 gates for domestic and international flights. The additions will allow the airport to double its passenger capacity to 34 million annual passengers.

After more than three years of work, we’re taking a moment to celebrate the project, by the numbers:

  • Tampa International Airport Expansion Stats

TIA Expansion Details

Breath of fresh air.

The project adds 55,000 square feet to the Main Terminal, including more than 23,000 square feet for new outdoor terraces.

Up, up, up and away.

The project includes the renovation of 24 elevators and the replacement of 1,112 linear feet of escalators.American Football Field

Go long!

The area of the Main Terminal’s third floor currently undergoing renovations is roughly 270,000 square feet, the equivalent of four and a half football fields.

People on the move.

The automated people mover features 7,300 feet of track and travels from the Main Terminal to the rental car center. A typical trip is expected to take about 4.3 minutes. The initial people-mover is designed to carry 2,700 passengers per hour. Eventually, it could handle up to 6,500 per hour.

That’s a lotta tile.

Crews have placed roughly 114,000 square feet of new tile flooring.

Pour it on!

It will take roughly 200,000 cubic yards of concrete – 25,000 truckloads – to build the automated people mover and rental car center.

Pick a car, any car.

Tampa International Airport’s rental car center clocks in at 2.6 million square feet – large enough to hold more than 5,300 vehicles at a time. The center features eight 25,000-gallon fuel tanks and 30 car washing stations. At its peak, it can handle 1,541 rentals and 1,650 returns per hour!

A solid structure.

The facilities will also require 14,000 tons of steel, including 9,000 tons of rebar and 5,000 tons of structural steel.

Mobilization Funding’s customers helped to make this project possible. What projects are you excited about? Mobilization Funding’s unique funding platform can provide you with the dollars you need to achieve your company’s goals.

American Manufacturing: Making America, American Made

Why is Made in America Valuable to Manufacturing? In the last few years, “Made in America” has evolved from a nostalgic slogan into a strategic movement for U.S. manufacturing. Deloitte‘s Center for Government Insights called it a new “American manufacturing renaissance. With a focus on bolstering domestic manufacturing, the United States has an opportunity to […]

Work in Progress Financing: The Secret Weapon for Project-Based Manufacturers

Learn how Work in Progress (WIP) financing helps manufacturers bridge cash flow gaps, fund materials and labor, and scale production without giving up equity. In project-based manufacturing, cash flow timing, not demand, often constrains growth. You need to purchase raw materials, pay labor, absorb overhead — long before your customer pays. That mismatch can strangle […]

The Top Bidding Mistakes Contractors Make and How to Fix Them

Bidding mistakes can cripple a construction contractor company’s growth and limit its profits. Many contractors, however, are unaware that they’re making these mistakes. At Mobilization Funding, we’ve reviewed thousands of contracts—and the bids that won them. Here are the top bidding mistakes we see and how to avoid them. Bidding to Win, Not to Profit […]