How does your business calculate the right bid for a job? Do you sort out the job cost and then increase it by a third? Do you use the “10 and 10” method, adding a 10 percent overhead and 10 percent profit? Are you able to differentiate between margin vs. markup? When is the last time you double checked those figures?

Financial expert George Hedley estimates that at least three-quarters of installation contractors don’t know how to estimate the markup they’ll need to cover job costs plus overhead and still turn their projected profit margins. Larger companies may find that their markup needs to be higher to cover increased overhead costs or to ensure that current or future investors are seeing healthy profit margins.

Understanding the difference between margin and markup is critical for contractors and business owners. That knowledge can strengthen their bidding process and result in more profit and less risk.

First, let’s define a few common terms:

Job costs include everything you’ll need to complete the work. This includes labor, materials, leased equipment costs, projected capital costs (if borrowing money for the job), bonding premiums, permits, gas, and other materials and supplies.

Overhead is all the bills and expenses not included in the above job costs that you will need to pay in order to operate your business. While this sometimes varies, it includes things like rent for your office, office-based support staff, some types of insurance, tools, equipment, bookkeeping, accounting, legal costs, owner’s salaries, outstanding debt payments and whatever else it might take to keep the lights on if you don’t have active jobs.

Net profit is the remaining amount after job costs and overhead are subtracted from the price. With net profit you can make capital investments in the company (new office, new equipment or machinery) and take distributions from the business in addition to your salary. A healthy business should be able count a net profit of at least 8%, experts say.

For more information about financial planning, bidding strategies and project management for your commercial construction company, download our free e-book.

What is the difference between margin and markup?

Markup is the sales price, minus the job costs. Margin is the sales price minus the job costs and minus overhead allocation.

Here’s an example:

Your total forecasted sales for the year are $1 million and your annual expected overhead costs at that level is $80,000. That’s an 8 percent cost of overhead. In other words, you need to tack on more than 8 percent to the cost of the job just to break even.

Many companies don’t take such a close look. Your business may be spending too much on overhead, or in times of growth, may not set aside enough to cover the cost of rent or to pay your own salary.

Let’s say you’re bidding on a job that will cost your company $200,000 to complete with materials, labor, and equipment, and you plan to bid $250,000. At 8 percent, your overhead allocation for this job would be $20,000.

Your markup would be calculated as follows:

Using the overhead, you can also calculate the margin:

There’s a big gap between thinking your company is making 20 percent net profit on a job when it is actually 12 percent or lower, and it’s a common mistake. That’s why it is critical that business owners take a close look at their overhead costs and use that knowledge to set bid amounts appropriately. At the end of the day, having too thin of a margin can leave your company vulnerable if something goes wrong on the job, like a weather delay or another trade’s issue.

Remember, that a good bid is never about just tacking on some standard percentage to your job costs. It’s about being precise about your business’s financial needs.